Essential Gantt for WPF is a MS Project-like Project Viewer with built-in grid, schedule and resource assignment constraints. It is designed to assist project managers in developing plans, assigning resources to the task, tracking task progress and so on. Some of the key features of Gantt control are: drag support for increasing and decreasing the Start and Finish Date of the Task, Drag and Drop support for the task within a row and automatic data synchronization between Grid and Chart. This page has information about the Gantt Control.

On this page:



Requirements

This control is available only for Windows WPF applications


Configuration

  1. Go to Displays / Draw.
  2. On the Components Panel, select Charts, then GanttChart.
  3. Click or drag-and-drop it on the Drawing area to use it.
  4. Double-click the object to open the configuration window.

Configuration

Description

Control Name

Defines the name used to identify the control.

Data Source

Specifies the data source used to populate the Gantt chart.

Visual Style

Enables you to customize the appearance of the control. The available options for Visual Style are:

VS2010

Blend

Metro

Office2010Blue

Office2010Black

Office2010Silver

Connector Stroke

Sets the color for the connector lines between tasks.

Schedule Background

Specifies the background color of the schedule area.

Schedule Foreground

Defines the text color for the schedule area.

Task Node Background

Sets the background color for the task nodes.

Grid Header Background

Specifies the background color of the grid header.

Grid Header Foreground

Defines the text color of the grid header.

Show Chart Lines

Toggles the visibility of lines between chart elements.

Show Non-Working Hours Background

Displays the background color for non-working hours.

Use Auto Update Hierarchy

Enables automatic updates for hierarchical task dependencies.

Show Baseline

Toggles the visibility of the project baseline on the chart.

Baseline Color

Sets the color for the baseline representation on the chart.

Baseline Thickness

Specifies the thickness of the baseline line.

Field Name

Selects the data field used for the specific column (e.g., TaskName, StartDateTime).

Column Name

Defines the custom name for the selected column.

With the instance below, it is possible to access all properties of Gantt Control.

To configure the Gantt control in the CodeBehind, create an instance for Gantt Control:

T.Wpf.Controls.TGanttControl  Gantt = this.CurrentDisplay.GetControl("controlname") as T.Wpf.Controls.TGanttControl;

Below are the properties listed, which are not exposed in the Gantt Control configuration window but you can still make use of it through the CodeBehind.

Property

Description

Predecessor

Enables you to set the relationship between the tasks.

GanttTaskRelationship

Contains four relationships: StartToStart, StartToFinish, FinishToFinish, FinishToStart.

ValidationMode

Contains two modes: Manual & Auto (Default value is Manual).

UseAutoUpdateHierarchy

Enable or disable the auto update hierarchy support.

ToolTipTemplate

Gets or sets the TaskBarCollection Property of GanttControl.

CustomScheduleSource

Gets/Sets the custom schedule items Source of the Gantt.

CellDate

Gets/Sets the current schedule cell date in the datetime schedule.

CellToolTip

Gets/Sets the current schedule cell tool tip.

CellTimeUnit

Gets/Sets the current schedule row time unit, like weeks, months and so on.

Content

Gets/Sets the current schedule cell content.

WeekBeginsOn

Gets or sets the starting day of a week in the project schedule. Default is Sunday.

FiscalYearBeginsOn

Gets or sets the starting month of a fiscal year. Default is January.

IsFYNumberingEnabled

Gets or sets the Fiscal Year Numbering. If this property is changed, it will be reflected in the schedule. By default, FY Numbering is set to false.

DefaultStartTime

Gets or sets the task starting time in a day. This is based on the GanttTime class of the Gantt control. Default is 9.00 AM.

DefaultEndTime

Gets or sets the task ending time in a day. This is based on the GanttTime class of the Gantt control. Default is 6.00 PM.

Weekends

Gets or sets the weekend days. Default value is Saturday, Sunday.

ShowWeekends

Enables or disables the weekend days in schedule. Default value is true.

ExcludeWeekends

Excludes or includes the weekend days in duration calculation. Default value is false.

ShowNonWorkingHoursBackground

Enables or disables the background for weekend days. Default value is true.

UseOnDemandSchedule

To get the expected performance you need to use dynamic schedule rendering.

BaseCellMaxLength

Splits the schedule cells by comparing the cell size with the API value on zooming-in

BaseCellMinLength

Merges schedule cells by comparing the cell size with the API value on zooming-out

ZoomFactor

Zooming takes place based on the ZoomFactor. The ZoomFactor should be greater than zero.

HighlightedItems

The items that are passed through this API will be highlighted in Gantt chart region. The items should be in linear form.

HighlightItemBrush

Specifies the color in which items should be highlight

CurrentDateLine

Gets the user-defined line for the DateTime indicator.

StickCurrentDateLineTo

Get/sets the StickCurrentDateLineTo property of the Gantt control. Default is Today.

Background

Gets/sets background color of strip line.

Content

Gets/sets the content of the strip line.

ContentTemplate

Gets/sets the content template of the strip line.

ContentTemplateSelector

Gets/sets the TemplateSelector of the strip line.

StartDate

Gets/sets the start date of the strip line.

EndDate

Gets/sets the end date of the strip line.

RepeatBehavior

Gets/sets the repeat behavior of the strip line.

RepeatFor

Gets/sets the intervals between the repeating strip lines.

RepeatUpto

Gets/sets DateTime value. The strip line will be repeated up to this value.

Style

Gets/sets the style for the strip line.

StyleSelector

Gets/sets the style selector of the strip line.

VerticalContentAlignment

Gets/sets the vertical alignment of the content present in the strip line.

HorizontalContentAlignment

Gets/sets the horizontal alignment of the content present in the strip line.

Type

Gets/sets the type of the strip line.

Position

Gets/sets the absolute position of the strip line for Absolute strip line type.

Height

Gets/sets the absolute height of the strip line for Absolute strip line type.

Width

Get/sets the absolute width of the strip line for Absolute strip line type.

ShowStripLines

Gets the user option to show the strip lines.

StripLines

Get/sets the collection of StripLineInfo from the user.

Column Mapping


Click the Add button to add a column to the list.

To map user table column with default column, you need to configure the field and column name properties.

Select Field and map the user column with column name textbox 

E.g.: In Field, we selected “TaskId” from the default column and I have mapped user column “ID” to the default “TaskId” column, as in the image above.

In user table, input for ParentId, PrecedesserTaskId and PredecessorDependencyRelation columns should be empty string or NULL if there is no data.

Click OK to save the configuration.


Runtime  