System integrators delivering complete solutions from design through deployment, managing projects, implementing standards, and ensuring successful delivery.
Your Role | Primary Focus | Essential Pages | Advanced Topics | |
---|---|---|---|---|
System Integrator | Full platform | Platform Overview | Solution Lifecycle | Security & Operations |
ProjectTemplate/ ??? Standards/ ? ??? NamingConvention.docx ? ??? ColorStandards.xml ? ??? AlarmPhilosophy.docx ??? UDTs/ ? ??? Motors.xml ? ??? Valves.xml ? ??? Instruments.xml ??? Graphics/ ? ??? Symbols.library ? ??? Templates.displays ? ??? Navigation.menu ??? Scripts/ ? ??? Calculations.cs ? ??? Reports.sql ??? Documentation/ ??? UserManual.docx ??? QuickStart.pdf |
Area_Equipment_Parameter
Area_Function_Type
Equipment_Vendor_Model
Phase | Duration | Deliverables |
---|---|---|
Discovery | 1 week | Requirements document, Site survey, Risk assessment |
Design | 2 weeks | Architecture design, Standards document, Design review |
Development | 4 weeks | Configuration, Programming, Unit testing |
Deployment | 1 week | Installation, Commissioning, Training |
Standard | Focus Area | Implementation |
---|---|---|
ISA-88 | Batch Control | Recipe management, phase logic |
ISA-95 | MES Integration | Level models, B2MML interfaces |
ISA-18.2 | Alarm Management | Philosophy document, rationalization |
ISA-101 | HMI Design | Display hierarchy, color standards |
ISA-99/IEC-62443 | Cybersecurity | Zones, conduits, security levels |
Area | Technique | Implementation |
---|---|---|
Database | Partitioning by date | Monthly partitions for historical data |
Database | Index optimization | Clustered index on timestamp |
Communication | Protocol efficiency | Use bulk reads, minimize polling |
Communication | Compression | Enable data compression |
Processing | Distributed computing | Split processing across servers |
Processing | Edge processing | Local data aggregation |
Client | Lazy loading | Load displays on demand |
Client | View optimization | Limit points per display |
Test Type | Focus | Method |
---|---|---|
Functional | I/O verification, Control logic, Alarms | Point-to-point testing |
Performance | Load testing, Stress testing, Endurance | Simulate maximum load |
Security | Access control, Audit trails | Penetration testing |
Acceptance | User requirements, Performance criteria | Witness testing |
Task | Hours per Unit | Notes |
---|---|---|
Tag Configuration | 0.1 hour/tag | Including alarming |
Display Development | 4-8 hours/display | Depends on complexity |
Device Integration | 2-4 hours/device | Including testing |
Alarm Configuration | 0.2 hour/alarm | Including documentation |
Testing | 20% of development | All test categories |
Documentation | 15% of development | User and technical docs |
Training | 16 hours minimum | 2 days on-site |
Document | Purpose | When |
---|---|---|
Statement of Work | Define scope and deliverables | Pre-project |
Functional Specification | Detail requirements | Discovery phase |
Design Specification | Technical design | Design phase |
Test Procedures | Validation methods | Development phase |
Training Materials | User education | Deployment phase |
Handover Documentation | Support transition | Project close |
Approach | Pros | Cons | Best For |
---|---|---|---|
Centralized | Single point of management | WAN dependency | < 5 sites |
Distributed | Local autonomy | Complex management | > 10 sites |
Hybrid | Balance of both | Higher complexity | 5-10 sites |
Issue | Investigation | Resolution |
---|---|---|
Performance degradation | System metrics analysis | Apply optimization strategies |
Communication failures | Network diagnostics | Verify routing, firewall rules |
Synchronization issues | Time server configuration | Configure NTP properly |
Template conflicts | Version comparison | Implement version control |
Deployment failures | Installation logs | Verify prerequisites |